Sprint 1 backlog refinement

Historical Sprint 1 evidence

This page preserves a reconstructed Sprint 1 refinement record. It is not a current backlog; see the Scrum records overview for its evidence and inference boundaries.

FieldRecord
Reconstructed dates11–12 August 2026
TriggerThe first vertical slice was implemented and deployable, but release evidence and the remaining Basic-tier journey were not yet decomposed sufficiently
EvidenceGitea issue creation history, the committed week-two issue plan, the Basic-tier issue plan, and subsequent implementation commits

This page records backlog changes that are visible in Gitea and Git. It does not claim a single uninterrupted refinement meeting or invent exact votes, estimates, or quotations that were not retained.

Inputs reviewed

  • the original Sprint 1 issues #10–#21;
  • the deployed authentication/location vertical slice;
  • release coordinator issue #20;
  • outstanding documentation, database-release, accessibility, privacy, and E2E evidence;
  • unresolved challenge, reward, card, deck, battle, authoring, and account lifecycle decisions; and
  • team ownership boundaries for product/Web, API/security, data/infrastructure, and quality/delivery.

Refinement on 11 August: release-quality backlog

The first refinement pass added focused work rather than hiding it under the general release issue:

IssueRefined outcomeRecorded owner
#43Field-test and calibrate location eligibilityKevin
#44Validate the accessible mobile journeyKevin
#45Review deployed authentication, CORS, and privacy boundariesUzair in current Gitea metadata; the committed plan originally described Tyron as owner, so the reassignment/history should be read from Gitea
#46Define the challenge and attempt API contractTyron
#47Make database release repeatableUzair
#48Rehearse PostGIS migration and recoveryUzair
#49Design challenge, reward, and ownership persistenceUzair
#50Add deterministic vertical-slice E2E coverageCaleb
#51Refine visual identity and frontend presentationKevin

Refinement rationale

  • Release quality was separated into independently reviewable security, accessibility, recovery, E2E, and presentation work.
  • Unvalidated numeric thresholds remained field-test tasks instead of becoming undocumented requirements.
  • Challenge/reward persistence and the API contract were prepared as design foundations, not silently treated as part of the already delivered location slice.
  • Team load was made visible. The committed plan explicitly warned that Kevin's visual and validation load exceeded the nominal week allocation and allowed non-blocking polish to carry forward.

Refinement on 12 August: remaining Basic-tier decomposition

The second pass decomposed the complete game loop into issues #62–#80:

  1. resolve product and governance decisions;
  2. establish local player profiles, roles, and account lifecycle;
  3. add challenge, attempt, card, reward, and ownership persistence;
  4. implement authoritative challenge start, marking, timing, and atomic rewards;
  5. expose card collections and starter grants;
  6. implement saved-deck persistence and player management;
  7. implement deterministic CPU rules, persisted matches, and history;
  8. implement protected author APIs and the author console; and
  9. seed and validate the complete demonstrable Basic journey.

The dependency order prevented the Web client from inventing protected rules before API, database, and product decisions existed.

Planning discrepancy retained for transparency

The committed artifact docs/planning/wits-quest-sprint-2-gitea-issues.md calls issues #62–#80 a Sprint 2 plan. Current Gitea metadata records those issues under the Sprint 1 milestone, and their work was completed within the same August delivery period. This record does not silently choose one label: it treats 12 August as a major mid-delivery refinement while preserving the naming discrepancy for review.

Resulting backlog policy

  • A backlog item is ready when its user or system outcome, owner, dependencies, acceptance criteria, security/data constraints, and evidence expectations are clear enough to implement.
  • Priority follows the dependency chain and release risk, not merely visual appeal or issue age.
  • Manual and external checks stay visible as checks; they are not converted into automated passes.
  • New findings become focused issues instead of silently broadening the active implementation branch.
  • Work that cannot fit without compromising testing, security, accessibility, or documentation is carried forward explicitly.

Refinement outcome

The refined backlog transformed one deployable location slice into two clear tracks: evidence needed to release that slice responsibly, and dependency-ordered work needed to complete the Basic game loop. Subsequent Gitea history shows that the resulting issues were assigned and closed, but each issue and its pull request remain the source of truth for completion evidence.

AI declaration

This retrospective refinement record was generated with assistance from Codex[GPT-5] using repository and Gitea evidence. Inferences are labelled and are not presented as verbatim historical discussion. The historical-status notice was added with assistance from Codex-CLI[GPT-5].